This website uses cookies primarily for visitor analytics. Certain pages will ask you to fill in contact details to receive additional information. On these pages you have the option of having the site log your details for future visits. Indicating you want the site to remember your details will place a cookie on your device. To view our full cookie policy, please click here. You can also view it at any time by going to our Contact Us page.

UK company fined after tank farm explosion

02 October 2017

In September, Liverpool Crown Court heard that on 19 January 2015, contractors of ESL Fuels Ltd cut into a sealed pipe using a grinder. The pipe, which was attached to a tank, was being used as part of a waste oil recovery process at their North Blend Tank Farm. Flammable gases within the pipe ignited, resulting in an explosion within the tank and the tank lid and vent pipe being partially detached and projected over a raised walkway.

An investigation by the Health and Safety Executive (HSE) found that the company was having difficulty with the waste oil recovery process which was foaming out of the vessel and filling its bund.

The company’s tests were inadequate and failed to identify the cause of the problem which was generating flammable carbon monoxide gas. A decision was taken to connect the vessel by pipework to an emergency relief dump tank to prevent a potential catastrophic overpressure in the tank but the safety implications of this modification and its design were not risk assessed. HSE also found systemic failings with the company’s management of contractors and an inadequate Permit to Work system.

ESL Fuels Ltd, based at the Stanlow Oil Terminal near Ellesmere Port, pleaded guilty to breaching Section 3(1) and Section 2(1) of the Health and Safety at Work Act 1974 and has been fined £100,000 and ordered to pay costs of £17,000.

Speaking after the hearing HSE inspector Matthew Lea said: “Even though nobody was injured this incident could have been prevented if the problems with the process and the subsequent design modification had been properly investigated, risk assessed and dealt with, and if the work of the contractors had been adequately controlled.

“HSE has brought this prosecution because failures took place that could have resulted in death or serious injury and we believe every person should be healthy and safe at work.”