This website uses cookies primarily for visitor analytics. Certain pages will ask you to fill in contact details to receive additional information. On these pages you have the option of having the site log your details for future visits. Indicating you want the site to remember your details will place a cookie on your device. To view our full cookie policy, please click here. You can also view it at any time by going to our Contact Us page.

IAEA releases first report on safety of planned water discharge from Fukushima Daiichi site

03 May 2022

The International Atomic Energy Agency (IAEA) Task Force, which is reviewing Japan’s policy to discharge treated water from the Fukushima Daiichi nuclear power station against relevant international safety standards, released its first report on April 29.

Image: TEPCO
Image: TEPCO

The report summarises the overall progress in the technical preparations for the water discharge. It compiles the initial findings from the Task Force’s first review mission to Japan’s Tokyo Electric Power Company (TEPCO), the Fukushima Daiichi nuclear power station operator, and the Ministry of Economy, Trade and Industry (METI) in February 2022.

Director General Rafael Mariano Grossi welcomed the initial findings. “Japan has made significant progress in its preparations and the Task Force is satisfied that TEPCO and METI have identified the appropriate next steps for the water discharge scheduled for 2023,” he said. “The work will continue so the Task Force can provide its conclusions before the discharge”.

The report includes a summary of the Task Force’s review and assessment activities across a range of topics such as the characteristics of the Advanced Liquid Processing System (ALPS) treated water, safety related aspects of the system built to discharge the water, the radiological environmental impact assessment, regulatory oversight, source and environmental monitoring programmes, occupational radiation protection, and the involvement of interested parties.

Preparing for the next steps in their review, the Task Force identified technical topics for further discussions and clarifications as Japan continues with its preparations. They also noted that TEPCO and METI put significant efforts into consulting with, and communicating to, interested parties and the public about the process to discharge the water. They look forward to seeing this continue as Japan approaches the 2023 water discharge.

“The Task Force highlighted the effective cooperation with the Japanese counterparts, which made it possible to clearly and promptly convey the results of the review mission to the international community” said Gustavo Caruso, Director, Department of Nuclear Safety and Security and Chair of the Task Force.”

The Task Force report is the first in a series of reports as the Task Force carries out more missions to Japan in the coming months and years to assess the water discharge against IAEA safety standards, which constitute the worldwide reference for protecting the public and the environment from harmful effects of ionizing radiation.

The report is available here.