This website uses cookies primarily for visitor analytics. Certain pages will ask you to fill in contact details to receive additional information. On these pages you have the option of having the site log your details for future visits. Indicating you want the site to remember your details will place a cookie on your device. To view our full cookie policy, please click here. You can also view it at any time by going to our Contact Us page.

600MW hydrogen plant with carbon capture granted planning permission in UK

20 February 2024

Equinor’s H2H Saltend, a 600-megawatt low carbon hydrogen production plant with carbon capture, has been granted planning permission by the East Riding of Yorkshire Council. One of the first of its kind and scale to be granted planning permission in the UK, Equinor says the plant will help establish the Humber as an international hub for low carbon hydrogen whilst significantly reducing carbon emissions.

Image: Equinor
Image: Equinor

The decision comes at a vital time, Equinor says, as the project prepares for a potential application into the Government’s forthcoming ‘Cluster Sequencing Track-1 Expansion’ process, which is expected to launch this year and will select decarbonisation projects in both the Humber and Teesside that can connect to the East Coast Cluster’s carbon capture transport and storage infrastructure by around 2030.

Due to be operational around the end of the decade and sited at the energy intensive Saltend Chemicals Park, to the east of Hull, H2H Saltend will help to reduce the park’s emissions by up to one third. To achieve this, low carbon hydrogen will be used in chemical processes by both Saltend-based and other nearby companies, as well as directly replacing natural gas in several industrial facilities reducing the carbon intensity of their products.

Hydrogen from H2H Saltend will also be blended with natural gas at Equinor and SSE Thermal’s on-site Triton power station. The amount of CO2 captured and safely stored in sub-sea aquifers as a result will be around nearly 900,000 tonnes per year, equivalent to taking about 500,000 cars off the road annually.

The H2H Saltend planning application was submitted to the East Riding of Yorkshire Council in July 2023. There have been three public consultation events in East Yorkshire and Hull since 2021 to present the project throughout the planning process, in addition to regular dialogues with local authority and parish councillors. No objections to the application were raised by any statutory body.

The UK Government is expected to launch the Track-1 Expansion competition from 2024. It is the next step of the Cluster Sequencing process, following selection of the East Coast Cluster as a Track-1 Cluster and subsequent selection of a first phase projects in March 2023, when Humber projects were unsuccessful.