Audit at StatoilHydro's facility at Mongstad
07 January 2009
During the period 23-24 September 2008, the Petroleum Safety Authority Norway (PSA) conducted an audit of crane and lifting operations at StatoilHydro's (SH's) process facility at Mongstad.
SH's governing documents have been used as a basis for operation of the facility and, in addition to the regulations, have also been used as a basis for the audit. The audit was conducted in the form of interviews with selected personnel, verifications at the facility and reviews of documentation.

Audit at StatoilHydro's facility at Mongstad
Two nonconformities were observed in relation to deficient certification of the bridge at Quay 7 and mobile cranes used at the facility without audio or visual warnings in the event of overloads.
Three improvement items were also observed in relation to operational, organisational and technical factors.